UK

Variations, Time Limits and Unanticipated Consequences

Ronan Champion
May 2007
A paper based on the second prize entry in the SCL Hudson Prize essay competition 2006, presented to a meeting of the Society of Construction Law in London on 1st May 2007

The 1999 FIDIC suite of standard forms, followed by NEC3, introduced clauses requiring formal notices by contractor to employer for events which may give rise to a claim (including variations), with a short time-limit for such notices and the claim being barred if notice is n

The Impact of 'Midland Expressway v Carillion Construction (No 2)' on 'Equivalent Project Relief' in PFI Transactions

Hamish Lal
November 2006
A talk based on a paper given to the Society of Construction Law in Manchester on 4th April 2006.

In PFI projects, the Project Company is usually so thinly capitalised that it is important to protect its capital and cashflow. One aspect of this is to ensure that subcontractors' rights and obligations are fully ‘back-to-back' with those of the Project Company.

Is Single-point Design Responsibility under JCT 05 Illusory?

Professor Peter Hibberd

October 2006

A paper given to the King's College Construction Law Association on 24th November 2005.

The author considers first what single-point design responsibility is, why it is pursued, and how it has been and is being sought.  He then moves on to consider the way contractual arrangements have developed, the wording that has been used and the extent to which the contract forms have been successful in achieving their objectives in regard to liability for design.